Emergency Services Expansion Update – July 2, 2026
Basement, Level 1, and Level 3 mechanical, electrical, and plumbing installations continue. Also in progress are electrical and plumbing in-wall on Level 1; interior wall layouts; elevator 17/18 shaft wall drywall from Levels 1-5; and door frame installation in stairwells and interior walls. Door frames are currently being installed in stairwells and interior walls, and penthouse framing has begun. Parking garage area grading is also ongoing. Nearing completion are the stairwell shaft walls and handrails on all levels, along with the exterior curtain wall on Levels 4-6 on the west side. Potential Operational Impacts Tudor