Here’s what our team shared about the progress of their work so far this month:
- Sidewalks in the courtyard have been poured.
- Phase 5 interior has been fully painted.
- Work has begun on the laundry rooms.
- Curtain walls have been completed and installed.
Note: “Phase” refers to the area or section being worked on. Each phase includes the first floor, second floor, and roof. See Phase map below.
Upcoming Milestones:
- Finish installation of both elevators
- Complete flooring of corridors
- Complete courtyard landscaping
This is a new build construction project on the corner of Ambassador Drive and Elmore Road. There should not be direct impacts to departments, although visitors to campus will most likely notice the construction activity. Noise levels will rise in the immediate vicinity due to heavy equipment operation.