Crews have reached an exciting milestone in the construction of the Skilled Nursing Facility (SNF) project this month. On October 16, the building’s final interior and exterior footings and the stem walls were completed. This is big news, as the last significant milestone achieved in this project was in March of 2025 when site preparation and general foundations were completed.
As cold weather creeps in, a temporary gas line has been installed on site while crews continue to install siding for phase 1. Framing of the first-floor walls is still ongoing, as is fireproofing of the second floor in phase 1.
Upcoming Milestones:
- Receive the last two shipments of steel
- Fireproof in phases 2 and 3
- Move to permanent utilities for the facility
Learn more about the SNF project, here.