Skilled Nursing Facility Update – Feb. 24, 2026 

Work continues through the winter on the Skilled Nursing Facility. Here’s what our team is working on and has accomplished thus far:  

  • Backfilled phase 6 & completed the plumbing prep  
  • Weather barrier & base flashing were installed in phase 4 for the windows 
  • Framed the soffits in the corridor of phases 1 & 2  
  • Fire stopping & caulking underway to all wall penetrations and transitions  
  • Work continues on the domestic & waste lines of phase 4   
  • Continued steel erection in phase 5  


Note: “Phase” refers to the area or section being worked on. Each phase includes the first floor, second floor, and roof. See Phase map below. 

Upcoming Milestones: 

  • Prep for and install storefront windows  
  • Electrical homeruns to be ran to the racks  
  • Move to permanent utilities for the facility 


This is a new build construction project on the corner of Ambassador Drive and Elmore Road. There should not be direct impacts to departments, although visitors to campus will most likely notice the construction activity. Noise levels will rise in the immediate vicinity due to heavy equipment operation. 