There are fewer coats out there and we’ve even spotted someone in a short-sleeved shirt! Here’s what our team shared about the progress of their work so far this month:
- The ICF wall was poured in phase 6
- Column bases are secured in preparation for the concrete pour next week
- The tent was removed from phase 5 and roof installation is underway
- Phase 4 sheet rocking is complete
- Trees have been cleared and ground thaw is down for the Chugach work
- Sprinkler work is underway for phases 3-5
Note: “Phase” refers to the area or section being worked on. Each phase includes the first floor, second floor, and roof. See Phase map below.
Upcoming Milestones:
- Re-route gas lines for permanent service with Enstar
- Chugach to set up permanent power to the facility
- Finish the last of the remaining curtainwall windows
This is a new build construction project on the corner of Ambassador Drive and Elmore Road. There should not be direct impacts to departments, although visitors to campus will most likely notice the construction activity. Noise levels will rise in the immediate vicinity due to heavy equipment operation.