Over the last couple of weeks, iron workers have been performing work in phases 2 and 3 of the Skilled Nursing Facility (SNF) project. Concrete has been poured up to the top of the wall in phase 3, and the roof decking in phases 1 and 2 has been welded down.
When phase 2 of the iron work is completed, construction crews will begin storm drain work. This week, they are installing the main plumbing branch lines and punch list framing. Recently, all concrete break tests passed.
Upcoming milestones:
- Interior Build out: April 2025 – December 2026
- Porte Cochere: June 2025 – August 2026
- Hardscaping & Landscaping: April 2025 – October 2026
- Roofing August 2025 – December 2025
Construction is at the corner of Ambassador Drive and Elmore Road. There should not be direct impacts to services, although visitors on campus will most likely notice the activity. Noise levels will increase in the immediate vicinity due to the operation of heavy equipment.