Skilled Nursing Facility update – Dec. 10, 2025
As temperatures drop, construction crews are finding ways to keep work on track. Temporary tents have been set up to heat the concrete, allowing crews to continue their work. Reinforcement on the exterior courtyard ICF wall of phase 2 is now complete, and has passed inspections. Weather barriers are also being installed in preparation for exterior window installation, and mechanical contractors are installing electrical wiring on the first floor. Upcoming Milestones: Construction is underway at the corner of Ambassador Drive and

Emergency Services Expansion Update – December 10, 2025
With one more month of 2025 remaining, basement concrete work is nearing completion, and stairs have been installed in three locations. Pan decking has been installed at zones 5-10 on level 3, and construction crews are continuing concrete slab work, which is expected to be completed sometime this month. As temperatures drop, levels 1 and 2 are now enclosed for heating purposes. Zone 10 (see map of zones below), level 4 steel is scheduled for completion in December, and steel

Enter to win Apple AirPods by pre-checking in at the ANTHC Airport Liaison Desk
Beginning Thursday, Dec. 4, patients who pre-check-in at the ANTHC Airport Liaison Desk at Ted Stevens Anchorage International Airport when they arrive will be entered to win a set of Apple AirPods Pro! We will be giving away one set of AirPods each week until Wednesday, Jan. 28. The Airport Liaison Desk is located on the baggage claim level, near Door 6. The desk offers a self-service kiosk screen where patients pre-check-in and will be automatically entered into the drawing

Emergency Services Expansion Update – November 25, 2025
As the Holiday season kicks off this week, basement concrete work is nearing completion, with basement column grouting already complete. Construction crews have begun pouring concrete for the level 1 deck and expect to complete it in December. Level 1 is being enclosed for heating purposes while crews continue their work. Zone 10 (see map of zones below), level 4 steel is scheduled for completion in December, and pan decking has been installed at zones 5-10 on level 3. Steel

Honor Your Lungs: Get screened for lung cancer
Lung cancer screening is an easy and effective way to help find lung cancer at an early stage when it is more likely to be cured with treatment, giving you more time to do the things you enjoy. Who can be screened for lung cancer? You may be able to get a lung cancer screening if you: *A pack-year is equal to smoking 1 pack (or about 20 cigarettes) per day for a year. Examples: 20 pack-year history = smoking

Skilled Nursing Facility Update – Nov. 18, 2025
With the Holiday season underway, construction on the Skilled Nursing Facility is progressing right on schedule. The building is now almost fully erected, with steel installation expected to be complete in December. Crews are working to bring the second half of the courtyard up to grade while the interior and exterior east courtyard walls are being built. Sprinklers are being installed throughout the building, and pre-rock drywall is being installed before the building envelope, which is expected to begin in

Skilled Nursing Facility update – Thursday, Nov. 13, 2025
Looking ahead to December, another significant milestone is on the horizon in the construction of the Skilled Nursing Facility. Mid-December is when crews estimate the building erection will be complete, and enveloping can begin. While steel erection continues, crews have begun installing all the essential electrical wiring and components, including cables, junction boxes, and outlet boxes, within the walls and ceilings before the drywall is installed. Framers have completed the first phase of work on the first and second floors,

ANTHC Airport Liaison Desk now open at Ted Stevens Anchorage International Airport
The Alaska Native Tribal Health Consortium (ANTHC) is improving and enhancing the system of care to make your travel smoother and more convenient, with the latest change being a new Airport Liaison Desk at Ted Stevens Anchorage International Airport. The desk is located on the baggage claim level near Door 6. The desk also offers a self-service screen to help you get where you need to go. Additionally, a staff Liaison will be available during posted hours to answer any

Skilled Nursing Facility update – Friday, Oct. 24, 2025
Crews have reached an exciting milestone in the construction of the Skilled Nursing Facility (SNF) project this month. On October 16, the building’s final interior and exterior footings and the stem walls were completed. This is big news, as the last significant milestone achieved in this project was in March of 2025 when site preparation and general foundations were completed. As cold weather creeps in, a temporary gas line has been installed on site while crews continue to install siding for

ANTHC Cardiology Clinic Moves to New Location October 31 – Expanding Services to Enhance the System of Care
The ANTHC Cardiology Clinic is moving to a new location with expanded services that will enhance the system of care for heart and cardiovascular patients. On October 31, the Cardiology Clinic will move from the Alaska Native Medical Center hospital to the second floor of the Healthy Communities Building (HCB) located at 3900 Ambassador Drive. When the Cardiology Clinic moves to its new location, it will expand to include 20 exam rooms, six testing rooms, and one procedure room. On-call

Emergency Services Expansion update – Oct. 23, 2025
Over the past couple of weeks, visible progress has been made on the Emergency Services Expansion (ESE) project. Now, when you walk outside of the Alaska Native Medical Center, the structural steel seems to progress daily. While construction crews work on actively setting that steel, basement concrete work is still progressing. The Basement wall at the northwest corner of the new structure was recently poured at Gridline 18, with column grouting ongoing and 65% complete. Potential Operational Impacts: The crane

Skilled Nursing Facility update – Monday, Oct. 6, 2025
As construction crews prepare for cold weather, an exciting milestone is just weeks away! On October 16, 2025, the building’s final interior and exterior footings and the stem walls were completed. This is big news, as the last significant milestone achieved in this project was in March of 2025 when site preparation and general foundations were completed. As crews continue to work on the building’s foundation, they are also pouring concrete walls, framing sections of the building, and have begun