Emergency Services Expansion update – Sept. 18, 2025

Crews are making significant progress on the foundation of the building. The basement concrete work is close to completion and the perimeter foundation walls have been formed and poured.

Zones 6 & 7 (see map below) are being prepped for steel installation that is scheduled for September 29-30. In the meantime, the steel structures in Zones 5 & 6 are being structurally racked and plumbed.

The placement of structural steel will continue through December.

Potential Operational Impacts:

The crane operation and steel installation are expected to have minimal impact on hospital operations. However, there may be some disruptions due to noise or vibration between September 25-26, when workers are scheduled to install a structural steel beam in Zone 5.

Additionally, Stairwell 6 closure is scheduled to begin in October and run through the Spring of 2027. See the below image for more detail.