Emergency Services Expansion Update – October 1, 2026 

Emergency Services Expansion Update – October 1, 2026 

Basement, Level 1, and Level 3 mechanical, electrical, and plumbing installations continue.  

Also in progress are the installations of elevators 15 and 16; the closing with drywall of Level 1 exam rooms; Level 7 roofing (the roof is roughly 90% complete); and the Northwest tower brick demolitions for the tie-in to the skybridge. 

Recently completed work includes the Level 3 south roof, the first section of the north roof, the level 6 connector bridge roof, the parking garage bottom level (concrete and is being prepped for the second level structure), and the liquid oxygen (LOX) concrete pad on the west side of the structure has been replaced.   

New fuel tanks on the west side have been set and the construction area will be repaved by 10/3/26. New LOX tanks will arrive in the coming weeks. 

Potential Operational Impacts 

Civil work at the north end of the parking lot may cause some noise and will continue through Fall 2026. 

Demolition and installation work on the west side of the hospital may cause some noise and will continue through late Winter 2026.  

Busway work will impact some areas of the existing basement through early 2027.  

A temporary liquid oxygen (LOX) trailer will supply building oxygen during the demolition and replacement of the existing LOX storage tanks. This Temporary LOX Supply System will be in place from 8/24/26 to 10/6/26.  

Stairwell 6 closure is ongoing and is scheduled to run through the Spring of 2027.  

Elevator 8 will be shut down from 9/29/26 to 10/2/26. 