Emergency Services Expansion Update – November 25, 2025

As the Holiday season kicks off this week, basement concrete work is nearing completion, with basement column grouting already complete. Construction crews have begun pouring concrete for the level 1 deck and expect to complete it in December. Level 1 is being enclosed for heating purposes while crews continue their work.

Zone 10 (see map of zones below), level 4 steel is scheduled for completion in December, and pan decking has been installed at zones 5-10 on level 3. Steel structure placement is ongoing and will continue through December.

Potential Operational Impacts:

The crane operation and steel installation will have minimal impact on hospital operations. There may be some disruptions due to noise or vibration as workers progress. The closure of Stairwell 6 is ongoing and is scheduled to continue through the Spring of 2027.

The project is on track for completion in Spring 2028.  