Basement, Level 1, and Level 3 mechanical, electrical, and plumbing installations are in progress. Drywall installation is in progress in the basement and on Level 1 interior walls, as are the in-wall rough ins of conduit and electrical boxes on the Level 1 interior wall. Level 1 interior wall framing more broadly is also ongoing.
Air Handler Units are being prepped for connection at Level 3.
Concrete slab work is completed on Levels 1-5.
Upcoming construction for the month includes: exterior framing on Level 1; exterior curtain wall work; and construction commencement on the West side of the hospital for fuel storage.
Potential Operational Impacts
West side of the site will be impacted for foot and vehicle traffic through the Summer of 2026.
Brick demolition on the east side of the existing hospital building will cause noise and vibration.
Air intake plenums installed to improve air flow may cause some noise.
Stairwell 6 closure is ongoing and is scheduled to run through the Spring of 2027.