Emergency Services Expansion Update – May 21, 2026 

Basement, Level 1, and Level 3 mechanical, electrical, and plumbing installations continue, as is interior wall framing on Level 1.  

We have moved on to drywall top out in the Level 1 interior walls, and fireproofing on Level 4.  

Concrete slab work has now been completed on Levels 1-6, and the structural steel supports have been placed for elevator shaft 15/16.  

Upcoming construction this month includes exterior framing on Level 1 and exterior curtain wall work.  

In June, work at the north end of the parking lot will commence, and demolition work will begin on the west side of the hospital. 

There are also plans for elevator shaft 9 to be upgraded into a 2-hour rated MEP shaft assembly. 

Potential Operational Impacts 

Existing elevator 8 will be temporarily unavailable during daytime hours until the second week of June. 

The west side of the site will be impacted for foot and vehicle traffic through the Summer of 2026. 

Brick demolition on the east side of the existing hospital building will cause noise and vibration. 

Air intake plenums installed to improve air flow may cause some noise. 

Stairwell 6 closure is ongoing and is scheduled to run through the Spring of 2027.  