Emergency Services Expansion Update – June 18, 2026

Basement, Level 1, and Level 3 mechanical, electrical, and plumbing installations continue, as does work on the drywall finishes of the basement walls. Also in progress is electrical and plumbing in-wall on Level 1; layout for Core and Shell for Levels 1-6; and interior wall layouts throughout the structure. 

Demolition and installation work will continue on the west side of the hospital through 2027 for fueling and liquid oxygen infrastructure.  

Elevator 17/18 shaft wall drywall has started and stairwell shaft walls and handrails are almost complete on all levels. Exterior curtain wall work has also begun.

Cooling tower and units have been installed and housekeeping pads have been completed in the heat exchanger room. ​

Upcoming construction this month includes civil work at the north end of the parking lot that will continue through the summer of 2026.  

Potential Operational Impacts 

The west side of the site will be impacted for foot and vehicle traffic through the Summer of 2026. 

Brick demolition on the east side of the existing hospital building will cause noise and vibration. 

Air intake plenums installed to improve air flow may cause some noise. 

Stairwell 6 closure is ongoing and is scheduled to run through the Spring of 2027. 