Emergency Services Expansion Update – December 10, 2025

With one more month of 2025 remaining, basement concrete work is nearing completion, and stairs have been installed in three locations. Pan decking has been installed at zones 5-10 on level 3, and construction crews are continuing concrete slab work, which is expected to be completed sometime this month.

As temperatures drop, levels 1 and 2 are now enclosed for heating purposes. Zone 10 (see map of zones below), level 4 steel is scheduled for completion in December, and steel structure placement is ongoing and will continue through January 2026.  

Potential Operational Impacts:

The crane operation and steel installation will have minimal impact on hospital operations. There may be some disruptions due to noise or vibration as workers progress. The closure of Stairwell 6 is ongoing and is scheduled to continue through the Spring of 2027.

The project is on track for completion in Spring 2028.  