Basement and Level 1 drywall, mechanical, electrical, and plumbing installations are in progress. Air Handler Units are being prepped for connection at level 3.
Hanger installation for ceiling infrastructure is ongoing on Levels 1 and 3. Brick demolition is ongoing at the east side of level 3 on the existing hospital.
Level 1 interior wall framing has started, and fireproofing of structural steel on Levels 2 and 3 is complete.
Upcoming construction includes: Work on Level 6 concrete placement and Level 1 exterior framing is expected to commence later this month; Fuel storage infrastructure on the west side of the hospital and exterior curtain wall work will commence in May; and work on the north end of the parking lot will commence in June.
Potential Operational Impacts
Air intake plenums installed to improve air flow may cause some noise.
Brick demolition will cause noise and vibration. However, the majority of the demolition is on the exterior of mechanical spaces and away from occupied spaces.
Stairwell 6 closure is ongoing and is scheduled to run through the Spring of 2027.